The Indoor airPLUS Construction Specifications Version 1 (Rev. 03) may be used by builders and Raters immediately.

 

Homes permitted on or after January 1, 2016 must use the Revision 3 Construction Specifications and Verification Checklist. For homes permitted before January 1, 2016, partners can use either Revision 2 or Revision 3 if desired. The Rater may define “permit date” as either the date that the permit was issued or the date of the contract on the home. Raters should complete only one Indoor airPLUS Verification Checklist per home.

 

Download the Indoor airPLUS Version 1 (Rev. 02) Construction Specifications -- https://www.epa.gov/indoorairplus/indoor-airplus-program-documents.